Building Approach
- Site visits by our engineer occurred during work
- Building team sign off and health and safety sign off for reinstalling top and lower balustrade to original height
- Approval to have individuals stay and work on site both private upstairs and public while building work ensued was granted.
- The council understood the uniqueness of the projects approach and allowed lee-way as long as certain requirements were met including;
- Fire Alarm Installation
- No public access on top deck until remedied
- Fence around balcony to ensure health and safety was adhered to due to missing balustrades and other damage to the house
Continue to Worked Areas